At the time this article was written John
Way was project manager of the Province House restoration project. An article
by him on renovations to the exterior of Province House appeared in the Summer
1982 issue of this review.
The restoration of the "cradle of
confederation" has been carefully programmed over a period of tour years
and is now virtually complete. It is anticipated that the restoration of the
building to its appearance in 1864 will attract many Canadians to Charlottetown
where the movement toward Confederation really started.
An agreement between Prince Edward Island
and the federal government has designated certain areas of the building for use
by the respective governments. The province retains ownership of the building
and will use it for annual sittings of the Legislature. The federal government
will interpret those areas associated with the 1864 Confederation Conference.
Certain other areas were designated as joint use areas by the province during
Legislature sittings and the federal government during the remainder of the
year.
The agreement provides that the
Confederation Chamber, the Clerk of the Council Office and the Library be
restored to the appearance of the rooms in 1864 (the year of Confederation
meetings). The corridors and stairs leading to these rooms are to be treated in
a similar way. Following negotiations with the province four offices on the
ground floor are also being restored to the same period. Other areas of the
building would be used for modern interpretative purposes.
Prior to starting any interior restoration
work, it was essential to confirm the construction and location of original
walls, floors, stairs, ceilings, doors, windows etc. The specifications gave a
good indication of the original construction but so many changes had been made
over the years that it was difficult to decide which parts of the building were
original. Historical research gave some indication when major repairs were done
but no drawings or documentation were available. Physical investigation
revealed that the plaster in the areas to be restored was not original and in
fact had been installed over insulation board making it out of original line.
This change revealed a number of situations where wood trim had been changed to
accommodate these modifications. There were other surprises too.
In the attic evidence of vertical plastered
shafts leading to the roof was found. These were obviously used as roof lights
and photographs taken in the early 1900s confirmed their size and location. We
anticipated that these provided light to the third floor corridor leading to
the public gallery, however, further investigative work revealed a large
opening in the floor below the roof lights which provided natural light to the
second floor corridor. Notches in the beams around the opening illustrated the
extent of the balustrade providing protection to the open space. There were two
such skylights. The lack of gas or electric lighting in the 1850s made natural
light an important feature in a new building of this era.
In one description of the building six
fireproof vaults were specified but only five could be located, all on the
ground floor. This remained a mystery until a built-in bookcase and the
surrounding plaster was removed exposing an 18" deep recess in the wall
surrounded by cut stone. This was the location of the sixth vault and was
restored using new fireproof doors.
Whilst all this investigative work was being
carried out a careful analysis and recording was made of existing structural,
mechanical, plumbing and electrical services contained within the building. The
original building was heated by fireplaces and Franklin stoves, lit by oil
lamps and had very little in the way of washroom facilities. During the years
many services were added and changed. Gas was used as lighting in 1855. Some of
the original gas pipes are still attached to structural framing. In recent
years a hot water heating system with convector heaters, a sprinkler system and
new washrooms were added on all floors. Many of the pipes, sprinkler heads, and
heaters were exposed thus conflicting with the historical authenticity of the
1864 period.
Engineering aspects of construction
As work progressed and the areas to be
restored were stripped of new finishes, it became apparent that some structural
modifications should be made to the building to level floors and ensure
structural integrity. Where major beams spanned long clear spans, they were
reinforced with steel members to ensure continued strength. The ends of beams
and joists bearing on the exterior walls had been damaged by dampness and wood
rot to a dangerous point. These beams were cut off and a new scarf about six
feet long was jointed to the existing wood beams. The new wood was treated with
wood preservative to give it a longer life when built into the existing masonry
wall. The replacement of wood tongued and grooved flooring was also essential
because large sections of the floor had worn down more than one inch from the
original thickness. These areas were replaced with similar wood.
After considerable analysis of the existing
main stair structure it was found that a number of major changes to the treads
and landings had been made which changed the "run" of the stairs. The
whole staircase had also deflected to some extent. Therefore new steel beams
were inserted at the landings to stiffen up and ensure structural stability for
the anticipated heavy visitor traffic. These were added without changing the
appearance of the stairs in any way. All steps were levelled and new treads
added as originally specified. As a result of the levelling, considerable work
had to be done to the balusters and handrail to ensure their strength and
appearance as they were in the 1850s.
The restoration of the west wing provided an
opportunity to reinstate the stairs from the basement to the second floor. The
only indication of the size and shape of the stairs was in a photograph of the
building taken in 1860 where the stairs appear through an open doorway. By
enlarging this area of the photograph sufficient information was obtained to
design the stairs as a reasonable facsimile of the original 1850s design. These
stairs were steep and narrow with winders making them even more difficult to
negotiate.
All services in restored areas are concealed
as much as possible and control of temperature in restored areas is provided to
preserve artifacts. The installation of an air conditioning system was
considered for the restored areas but due to space restrictions and
difficulties of confining the system to a relatively small area of the
building, this proposal was rejected.
The various types of heating available for
incorporation in the existing structure were analyzed with appearance of prime
importance. To minimize the impact of the heating system on the appearance in
the restored areas a hot air floor grille type unit was selected. This unit was
provided with hot water heating except on the second floor where there was
insufficient space to conceal the piping in the structure so electric heating
was used.
To supplement the heating system in the
Confederation chamber and Legislature chamber a simple ventilation system was
installed. This avoids the build-up of heat in both areas during the summer
months. The chimneys in use in the 1B50 period were used to conceal the air
intakes and exhaust and the ventilation equipment was located in the roof space
where it would not be a visible part of the structure.
In order to maintain the 1850s appearance of
restored areas, fireplaces were reintroduced into those areas that were identified
as having active stoves. Reproduction heating stoves of the period were
purchased and installed in the appropriate locations complete with connecting
flues to chimneys. These stoves and chimneys were not made active due to the
fire hazard and the cost of having to rebuild masonry flues through the
building to today's safety standards.
Modern fire regulations require that a
sprinkler system be installed in a building of this size. The concealment of
this system in the restored areas presented numerous problems but were
successfully overcome by using the basement and roof space to accommodate the
main runs of piping. As with all other services in the building additions had
been made to the electrical system over the years, and new outlets for equipment
were required. These additions had brought the system close to its maximum
capacity so it was essential that a new underground supply system be installed
before any new work was undertaken. Areas of the basement were used to install
the new switches and panels and all restored and renovated areas were rewired
to present day codes. In restored areas all new outlets were concealed behind
wooden baseboards and reproduction lighting fixtures rewired for electric
power.
Architectural restoration
Prior to the removal of material from
restored areas it was essential to carry out an analysis of the paint that had
been used on wood trim over the years and endeavour to arrive at paint colours
that had been used in the 1850s. This was achieved by taking small core samples
of paint from a variety of locations throughout the restored areas. These cores
indicated 1517 layers of paint in many locations but by the use of a special
microscope it was possible to obtain colours of paint at the various levels.
The colours selected were based on this analysis. In many cases there was
evidence of doors and trim being grained, stained and varnished.
In order to obtain more evidence of these
special finishes in different rooms it was necessary to strip through the
layers of paint to about the seventh or eighth layer, then very carefully
remove the last two layers to expose the original wood graining of the 1864
period. This painstaking work was done by Conservation specialists for sample
areas in Confederation Chamber, Library and Offices for door stain and grain
colours and corridors and Confederation Chamber for column marbleing. These
samples were used to match the new stain and grain finishes for shutters, new
and repaired doors, trim and baseboards in all restored areas. The graining in
Confederation Chamber is satinwood with an appearance of birdseye maple, in
theoffices dark oak, and in the Library a light oak.
All windows, shutters and trim in the
building were assessed with regard to reuse, repair or replacement. Most windows,
particularly on the upper floor were found to be original construction. These
were repaired as necessary with many sills and lower rails being replaced.
Almost all windows in the restored areas were reglazed with glass of the 1850s
appearance which was obtained from an old greenhouse before it was demolished.
Some windows in the restored offices on the ground floor had been replaced in
the early I 900s and were not the correct dimensions so new windows were made
to the correct sizes.
Exterior doors were replaced since they were
part glazed and not panelled as indicated in the historical records. Interior
doors had been moved to different locations in the building and many had glass
upper panels inserted. Most doors had all hardware removed, or modern type
locks added. Each door was carefully assessed in terms of the amount of
original material that could be used and the extent of repair and replacement
required. Many doors were repaired with new rails, stiles and mouldings. Some
were completely replaced with new ones and new brass hardware of the 1864
period was installed throughout the restored areas.
The extent of repair work required to doors,
windows, shutters and trim was considerable and could only be completed by a
crew of tradesmen on site working on each individual item and carrying out the
required repair work. This was carried out in a very dedicated manner by four
carpenters and two assistants. Work on new doors, windows and shutters was
contracted out to local carpentry shops.
Decorative plaster features such as ceiling
mouldings and lighting medallions and repairs to existing medallions were also
completed. These special features required the use of special "older"
methods of workmanship in order to achieve the required final finish. Special
mouldings and features were built up with many layers of plaster until the
final shape or profile could be sculpted. The mix for the plaster was as
originally specified in the 1850s and included the slaking of lime on site, an
unusual procedure for today's plasterwork.
During the final stages of the project, many
specialized items had to be produced in order to complete the restoration
process. The fire proof book vault required a new set of doors and special
hinges. The vault doors of the 1864 period were approximately four inches thick
made up of two sheets of quarter inch steel held apart by bolts at
approximately eight inch centres over the entire face of the door. The doors
were made in a metal fabrication shop and installed in the original stone
surround on metal printle type hinges. The end result was a successful
fireproof set of doors.
Lighting fixtures in restored areas were
replaced and new period reproduction chandeliers and wall fixtures were added
in the locations of the gas fixtures. The design of fixtures was based on some
original fixtures which were restored and rewired and other types of fixtures
of that particular period.
The final finishes to walls, floors, doors,
windows, ceilings. etc. were established following the colour analysis of the paint
samples. Generally speaking ceiling and wall finishes in the 1864 period were
limewash and this type of finish was used in restored areas where there was not
too much visitor traffic. In the stairs and corridor areas a modern paint
specially formulated to simulate a limewash was used so that it would not brush
off on peoples clothes and could be cleaned when required.
Floors in the restored areas were originally
finished carpeted over tongued and grooved boarded flooring. In some restored
areas the boarding had been removed or changed and in these cases new boarding
was installed. In other areas repairs were made to make the floor level and
ready for installation of carpets imported from Europe. A special type of woven
carpet following that originally purchased for the building was used and the
narrow widths were hand sewn on site to fit specific areas. In stairs and
corridors the original boarding was stained but in order to avoid excessive
wear on relatively soft wood stair treads and floors, and because of the heavy
visitor traffic, runners covering the heavy wear areas were installed. These
runners can be replaced inexpensively when worn out.